Friday, Mar. 04: DAY Shift
From Hall A Wiki
Revision as of 21:52, 3 March 2016 by Parkkj (Talk | contribs) (New page: Go back to Daily Run Plan Daily Run Plans <b>Previously...</b> * Set up beam through Compton chicane * Production run ? <b>Specific mission</b> * Note: 1/ Agreement with Hall-D ...)
Go back to Daily Run Plan Daily Run Plans
Previously...
- Set up beam through Compton chicane
- Production run ?
Specific mission
- Note:
1/ Agreement with Hall-D and Talked PD to set up the BCM calibration tomorrow
- Crucial: high beam current 30uA with FC & empty target
Instruction:
DOC1DOC2
- Experts on call (Dave/Julie/Thir/...)
- Calo. HV off
2/ Back to production mode
BPM/Spot++ Check
- After beam lost for considerable time (like beam study, pass change,...)
- Ask MCC to run 5uA wth carbon hole target and make sure you can see the hole through Spot++