Friday, Mar. 04: DAY Shift
From Hall A Wiki
Go back to Daily Run Plan Daily Run Plans
Previously...
- Set up beam through Compton chicane
- Production runs (YES!!)
Specific mission
- Note:
1/ Agreement with Hall-D and Talked PD to set up the BCM calibration (8:30AM)
- Crucial: high beam current 30uA(at least try) with FC & empty target
- Experts on call (Julie)
- Calo. HV off
- Instruction: DOC1DOC2
10:50AM (snap shot of BCM)
11:00AM Complete mission of BCM
HALOG:[]
2/ Back to production mode
BPM/Spot++ Check
- After beam lost for considerable time (like beam study, pass change,...)
- Ask MCC to run 5uA wth carbon hole target and make sure you can see the hole through Spot++