Wednesday, March 16, 2016 1:30pm EST
From Hall A Wiki
Last meeting: Wednesday, March 2, 2016 1:30pm EST
Agenda
- prototype coil
- status of collimator
Minutes
Attending: KK, Jason, Juliette, Jim, Ernie,
- prototype coil tests
- under SBU
- where?
- do at MIT Bates with SBU student/postdoc
- do at SBU with MIT folks traveling
- space for the prototype
- with 20 ton crane
- protoype coil cost ~$150k
- need a breakdown of what goes into that
- request a real bid
- need to put together a bid package
- what type of coil?
- hybrid, full scale
- hybrid, but shorter (same current densities, same cross-sections)
- simpler racetrack coil
- if shorter also could do Ernie's version also
- might not have a working coil if full size anyway
- need to "reduce risk"
- doing two shorter hybrid-like coils w/ the two different conductor cross-sections
- allows us to see if they can really produce bends
- allows us to see if one or the other cross-section works
- still allows us to test the bends
- change number of outlets so that we still end up with the same length water circuits
- if we built a full-size one it might not be a spare prototype anyway
- deadline of May 1
- collimator status
- temp limit 100 C
- pretty standard - no prototyping needing
- what's next for the collimators?
- Tasks for 2016