Wednesday, June 8, 2016 1:30pm EST
From Hall A Wiki
Last meeting: Thursday, April 14, 2016 11:00am EST
Agenda
- Javier's Pre-project Planning document, due soon (A-C3)
☑ List of major subsystems
☑ List of subsystems of each major system
☑ Persons responsible for each subsystem
☑ Schematic/list of subsystem cartoon
□ Estimate cost as well as possible (cite source: manufacturer, previous purchases, machine shop work, catalog, etc.) January 2016 Table
□ Labor estimate Labor
- Javier's Pre-project Planning document Labor and Timeline (C4-C5)
□ Packaging and shipping costs and timeline
□ Work timeline
□ Time for funds to come in
□ Procurement times
- Javier's Pre-project Planning document (C6 - L2 manager compiles information)
□ Procurement Profile
□ Labor Profile
□ Timeline for contracts, hiring, funds transfers
□ Cost and Risk
Cameron's MOLLER CAD to-do list
Minutes
Attending: Juliette, KK, Seamus, Cameron, Tyler, Rakitha, Jim
- Cameron's slides
- PMT shield
- moveable collimator
- between inner photon collimator and acceptance defining colimator
- concrete shield is downstream
- won't need to be cooled
- update e- and gamma envelopes
- "fix" detector locations
- shielding def'n into CAD
- Rakitha will make sure repository updated
- Seamus and Tyler will work to import into CAD