Thursday, May 11, 2017 11:00am ET

From Hall A Wiki
Revision as of 11:30, 11 May 2017 by Crowder (Talk | contribs) (Minutes)

Jump to: navigation, search

Last meeting: Monday, March 20, 2017 3:00pm EST


Agenda



  • Prototype coil
  • Future work (recommendations from review - not ready)
  • JLAB contract
  • Next meeting time



Minutes

Attending: Juliette, Seamus, KK, Jim, Jason, Ernie


  • Prototype coil
    • in contact with Emerson
    • almost done
    • waiting for final quote
    • Ernie looked over the location to check electrical power/water cooling
  • Future work (recommendations from review - not ready)
    • collimator/shielding - Tyler
      • ds petal is "only" a cleanup collimator
      • ds petal generates backgrounds - doesn't have to be right against the nose
      • going to move it as far upstream as possible - radiation on hybrid nose will go down by reduced solid angle
      • Cameron is working on the simulations
  • JLAB contract (end of May) - finish the cigar collimator design
    • we're in extension now - need a new contract
      • describe deliverables from old, define activities for new
    • quality control/testing for prototype
    • upstream cigar collimator
      • water-cooling/thermal was part of old contract
      • manufacturing/motion/supports in new
    • Prototype
      • old contract deliverable was getting bids
      • new contract is time from MIT for construction/quality control, testing
    • Downstream toroid
      • test prototype coil before going forward
      • failure mode analysis?


  • Next meeting time






Return to Teleconferences
Return to MOLLER at 11 GeV E09-005