Hadron DAQ re-installation

From Hall A Wiki
Revision as of 19:04, 10 March 2009 by Moffit (Talk | contribs) (Neutron Detector DAQ)

Jump to: navigation, search

Plan/Checklist for Re-Installing the BigBite Hadron DAQ (including Neutron Detector).

Hadron Package DAQ

  • Remove all NIM/CAMAC/VME modules that will not be used.
  • Replace Linear FI/FO in second NIM bin.
    • Recable all dE linear sums (L+R) from 50/50 splitters and to CAMAC Discriminators
  • Recable all E (dE) from x10 Amplifiers (50/50 splitters) to CAMAC Discriminators
  • Verify mapping of E and dE delay line from x10 Amplifiers to VME ADCs.
  • Cable E and dE scintillators from Hadron Package to DAQ Weldment Patch Panels

Neutron Detector DAQ

  • Acquire 2 NIM bins (300W) from Electron Package Frontend
  • Acquire 16 x10 Amplifiers (NIM Bin modules)
  • Acquire 16 CAMAC Discriminators
  • Acquire all patch cables
    • 240 for Patch Panel to x10 Amp
    • 240 for x10 Amp to discriminators
    • 240 for x10 Amp to Delay Patch Panel
  • Cable up and map all patch cables