Meeting 2023 12 06
GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am
Link to all previous meetings: GMn GEM Commissioning Meeting
Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!
GEM inventory for GEn-RP and GEp:
Work plan for GEn-RP
1. BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers. 2. Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs. 3. Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps. 4. Work on SBS GEM is 15 days until Feb 15. 5. Build the SBS GEM bunker after the SBS and HCAL moved into position. This may allow to put the bunker closer. 6. Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.