Long term Long term HAPPEX run plan by Kent

From Hall A Wiki
Revision as of 15:02, 28 August 2009 by Camsonne (Talk | contribs) (New page: HAPPEX ELog Logged in as "Alexandre Camsonne" List | New | Edit | Reply | Duplicate | Find | Config | Logout | Help Message ID: 1669 Entry time: Sat Aug 8 23...)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search
 HAPPEX ELog 	Logged in as "Alexandre Camsonne"	
List  |  New  |  Edit  |  Reply  |  Duplicate  |  Find  |  Config  |  Logout  |  Help 	   

Message ID: 1669 Entry time: Sat Aug 8 23:55:15 2009 Author: Kent Paschke Type: Other Subject: HAPPEX-III Run Plan

Here is a data dump of my notes on the HAPPEX-III run plan. Detailed prioritization/ordering does not have be done now, but I do need to separate needs from wants in the initial commissioning as well as better match up dependencies between the different steps.


Mon Aug 17 - Restore

Tue Aug 18 - Restore

Wed Aug 19 - Collab Tests

Thu Aug 20 - Collab Tests

Fri Aug 21 - Commission [1 pass] (Watercell, optics, lead detector low current studies)

Sat Aug 22 - Commission [1 pass] (Watercell, optics, lead detector low current studies)

Sun Aug 23 - Commission [1 pass] (Watercell, optics, lead detector low current studies)

Mon Aug 24 - Day shift: remove water cell. Liquify target. stay at 1 pass.

Tue Aug 25 - Pass change to 3-pass. Remove Lead target, position HAPPEX detector.

Wed Aug 26 - Commission [3 pass]

Thu Aug 27 - Commission [3 pass]

Fri Aug 28 - Commission [3 pass] -> Move to production


1-pass Commissioning: 8/20-8/25 o Optics + watercell. (Nilanga) [2 shifts] o Lead detector low current studies. (McNulty) [2 shifts] o Bullseye scan? o Arc Beam energy measurement Aug 22 (Arun) [1 shift] o Lead detector high-current test - Aug 24-25 (Kumar) [1 shifts] o 240 Hz noise study - Aug 25 (Kumar) [0.5 shifts]


3-pass Commissioning: 8-25 -? o Commission cryotarget [1] o Establish luminosity limits (target, radiation, source) [1] o Compton background reduction [1] [3] o Position compton photodetector (B. Quinn) [1] [3] o Electron detector commissioning (A. Camsonne) [1] [3] o Moller systematics study and commissioning (Sasha) [1 shift] [1] [3] o Mini-spin dance to tune wien angle (Sasha) [1 shift] [1] [3] o Establish trajectory on target (lumi? HRS optics?) [1] o 3-pass optics cross-check (Nilanga) [3] o position H-III detector in HRS FP. (Dustin) [1] o H-III detector Q2 measurement (Nilanga / Dustin) [1] o BCM calibration (Paschke) [0.5 shift] [1] [2] [3] o fixed-gain BPM calibration (Paschke) [0.5 shift] [1] [2] [3] o Dithering magnet checkout (Paschke) [0.25 shift] [1] [3] o HCBA qualification [1] [3] o commission charge feedback system [1] [2] [3] o IPM cavity triplet high-current commissioning [2] [3] o IPM cavity triplet nanoamp commissioning [2] [3] o target boiling / width studies

Notes: [1]: necessary for start of production [2]: can be done at 1 pass [3]: can be done without cold target


Special Measurements:

-- periodic -- o Moller measurements (more than 1/week, but frequency depends on Compton performance) o Q2 measurements. (not less than 1 per week) o detector linearity studies o BCM calibration. (not less than 1 in three weeks) o BPM fixed-gain calibration (not less than 1 in three weeks)

-- Single (or few) time -- o mini-spin dance to check transverse polarization (as needed) o Q3/Dipole rescattering rate study (2x?) o rescattering radiative tail cross-section study o beam energy measurement (3-pass) o Dummy Al Target background study ( at least 2x ) o Warm cryo-cell Aluminum background study o Transverse Asymmetry study? ELOG V2.6.5-1844