Meeting 2023 12 06

From Hall A Wiki
Jump to: navigation, search

GMn GEM commissioning Meetings: WEDNESDAY 10:30am - 11:30am

Link to all previous meetings: GMn GEM Commissioning Meeting

Please use sbs_gems mailing list for plots/communications and HALOG entries relevant to GEMs!


GEM inventory for GEn-RP and GEp:

  • Inventory and plan: [1]
  • HV upgrade tracker: [2]

Work plan for GEn-RP

  1. BBGEM work would start Dec 6th and end Dec 19th. This is the HV upgrades for the UV layers.
    • Vimukthi, Holly, Xinzhan, Saru + techs
    • Do we have what we need to do this?
    • Replace APVs?
  2. Transport recoil detector, active analyzer into hall in late Jan. Should happen after re-install of SBS GEMs.
    • Need to upgrade HV on recoil layers and test. Early Jan?
    • Vimukthi, Bhasitha, Saru, ?
  3. Remove the SBS GEM stack around Jan 25 for HV upgrades and APV repairs/swaps.
    • Work on SBS GEM is 15 days until Feb 15.
    • Will we swap modules to put the HV inputs on the same side?
    • What do we need to order now to be ready for this?
  4. Build the SBS GEM bunker after the SBS and HCAL moved into position.
    • Holly will work with engineers and techs, but this will happen maybe Feb timeframe.
  5. Arbitrarily put Joe B installing the GEM LV supply on Jan 8th. We will continue to use the electronics/LV in place while we upgrade and troubleshoot.
    • Holly, Vimuthi will coordinate with Joe
    • Need to verify this week what equipment we need.

DAQ updates (Ben, Bryan, Alex)