The Operational Safety Procedures (OSP) is a permit approved by the
Physics Division
for commissioning and operation of an experiment system and/or an entire
detector. To facilitate
experiment checkout, the experiment may desire that sub-systems be approved for
commissioning prior to commissioning of the entire detector. In this
situation, the EH&S
Review Coordinator should request that a Temporary Operation Procedure
(TOSP) be granted.
EQUIPMENT IDENTIFIED IN THE PRELIMINARY HAZARD
ASSESSMENT
SHALL NOT BE TURNED ON WITHOUT AN APPROVED TOSP OR OSP FROM
THE
PHYSICS DIVISION. A general guideline is that commercial equipment
generally does not
require a review prior to initial turn on. Experiment personnel should
consult with the EH&S
Review Coordinator if there is any uncertainty on the need for a review.
Eventually, as experiment checkout progresses and TOSPs and OSPs are
granted for
systems, all systems will be approved and operating. Prior to initial data
taking, the Associate Director for Physics
must certify the experiment readiness following the procedure documented in
the Jefferson Lab EH&S Manual. The process includes the following components:
- 1.
- Copies of signoffs from EH&S review committee(s). (This often is a
collection of partial OSP's)
- 2.
- Physics Division determination that the experiment is
covered by existing/new SAD.
(This means that the experiment complies with the
requirements of a
specific version of a Safety Assessment Document.)
- 3.
- Physics Division determination of the need for an
experiment Conduct of
Operations (COO) document. (A COO may not be required if it is
determined that
sufficient
engineered controls are in place to obviate the need for formal Conduct of
Operations.)
- 4.
- The Jefferson Lab Beam Containment Policy tasks the Radiation Control Group with
specifying and maintaining configuration control on radiation shielding. Radiation
Control Group reviews an experiments Radiation Safety Assesment Document (RSAD); their signature on the document indicates that radiation shielding is
adequate and all
configuration control items are in place. (Jefferson Lab is responsible
for providing
sufficient radiation shielding to protect experiment personnel as well as
Jefferson Lab personnel
and the general public. In some cases, specific components such as
collimators or beam
pipe must have their configuration maintained.
- 5.
- Copy of the experiment hazard communications document (usually part
of the COO).
- 6.
- Verification statement from spokesperson that any required procedures
are approved and in
effect. (In the unlikely event that safety procedures are required, the
experiment must
demonstrate to the Associate Director for Physics that these procedures are in place
and that
appropriate training has been given.)
The Running Condition specifies the requirements for operation of
beamline. Examples
of requirements are beam energy and intensity limits, magnet current
interlock limits, beam
enclosure interlock status, etc.. The Running Condition is drafted by the
experiment
collaboration and approved by the Physics and Accelerator Divisions. An
approved Running
Condition is documented in the Accelerator Division's ``Beam Authorization Sheet," which is required by the Operations Group before beam may be
transported to the
experiment.