SAGDH Septum and Commissioning Meeting
Kees de Jager
opened the meeting by discussing the schedule:
-
The septum magnet progress is slow
-
The June 15th delivery date will not be met, so the
first magnet will go
to the hall
to be cooled down
-
SAGDH will not be able to run in November and December
because G0 will
need polarized
beam, and no other halls will be able to use 3 GeV beam
-
Kees suggested that the collaboration should consider
the minimum amount of
beam time
needed to run the experiment
-
Possible running times:
-
Run part of experiment in October 2002, and finish
after Parity in 2003
-
Run in August 2003, after Parity (depends on G0 running
in Fall 2003)
-
Run in next gap of G0 run (early 2004)
-
Note: Collaboration needs to supply enough manpower
to setup
3He target in July
Since the first septum that will arrive
is for the R-arm, the collaboration is considering
switching the cell design so that
the 6 degrees side will be on the R-arm side
Alexandre Deur discussed the runplan and
issues:
-
Cell Status:
-
"ice cone" cells: no good cells yet, needs full
priority
-
"standard" cells: ~ 3 good cells, production
on hold
-
c1720, thin wall: 2 made by Mike, production
on hold (1 gone, 1 unfilled)
-
Important to produce a "ice cone" water cell for tests
-
Run Plan:
-
Possible switch the 6 and 9 degrees sides of the "ice
cone" cell
-
"New" accelerator schedule has 3 GeV running between
1.6 and 2.0 GeV
-
Added elastic runs (9 degrees, 1.6 and 2.0 GeV)
-
Empty cell runs to check wall contamination and radiative
tails
-
Only one positron run at the end of the experiment
-
Things to do:
-
At least 2 runs per setting
-
Extend 1.6 GeV data taking to larger nu
-
More detailed document
-
Alternative run plan (1 septum, 1 angle, ...)
-
Prioritize a minimum set of kinematics (need 3 GeV)
Paul Brindza discussed the status
of the septum magnets:
-
Four good coils with all pieces at BWXT
-
Software: Second version of PLC complete.
Operation software is
in development
and testing stage
-
Yoke and coil of first magnet complete. LN2 shields
added and fit checked
-
Yoke # 2 machining complete, waiting to finish the
first magnet
-
JLab's preparation work is well advanced for delivery
of magnet
-
Magnets will not be tested before putting them into
the hall
-
Expected delivery of first magnet: end of June,
Paul doesn't expect
until end
of July 2002
-
Septum # 2, Paul expects by late September 2002!
-
Magnets will take about 2 weeks to install and cool
down
Al Gavalya discussed the design Status:
-
~ 11 weeks of design completed by Susan Esp
-
~ 17 man weeks of work until completion
-
Collimator support is about 10% complete (4 weeks)
-
Need to prioritize and get more resources
Steve Lassiter discussed the field
clamp simulations:
-
Finished simulation including septum magnets, field
clamps, and helmholtz coils
-
The Bz component of the field will be 8-11 G, a factor
of 2 decrease on H0!
-
Result with no clamp and no holding field, gives a
gradient for
By = 77.3
mG/cm, and Bx and Bz ~ 0
-
With the clamp By = 11 mG/cm
-
Steve will simulate the septum and helmoltz coils without
the field clamp
-
If the gradient from any component is too large, compensation
coils will be used
John LeRose gave an overview on
the Septum controls:
-
Scott Higgins assigned to implement Septum magnets
into EPICS
-
Basic tools (essential to run)
-
on/off, Iset/Iout, and interlock status
-
Expert screen
-
Field readout (direct clone of HRS Dipole NMR screen)
-
Update "Standard Hall A Tools"
-
Extra line for septum (each spectrometer)
-
Modified P0 set (for each angle)
Doug Higinbotham discussed the
Septum Optics commissioning:
-
The full septum comissioning time has been scheduled
before SAGDH
-
No 3 GeV because of Hall B
-
Sieve slits will be put in and out by hand
-
Since there may be no 9 degree data, we should study
the flux of 2 septum Vs. one
-
No field mapping before the experiment due to the delay
in delivery
Ron Gilman discussed detectors for the
experiment:
-
Experiment will use standard detectors for both HRS
-
FPP in HRSL (?)
-
No S0 or aerogels (needed for hypernuclear)
-
Summer checks: detector checkout (Vince), upgrades
as needed,
experiment
monitoring, and avoid "stupid" problems
Ron Gilman discussed helicity monitoring:
-
Use new "G0" standard
-
Check A1n/g2n electronics (maybe disassembled)
-
"G0" test run needed, early July
Arun Saha discussed the Beamline:
-
A BCM calibration was done for super-Rosenbulth
-
Another should be done for SAGDH
-
Use OTR and Harp to monitor beam position and profile
Matt Poelker discussed the polarized
beam:
-
Experiment requirements include 15 muA with high polarization,
parity
quality
with independent control of feedback, and independent current ramping
-
Need to give beam requirements changes to the source
-
Independent IA (intensity asymmetry controller) and
piezo mirror installed for
tests at
Hall A
-
Feedback via epics can be implemented now
-
g0 to begin 10/02. Finding proper machine settings
may result in tune-time
Sirish Nanda gave an update on
the compton polarimeter:
-
Mirrors replaced and compton now works
-
Resident in FEL group, expert on compton optics
-
Root based analyzer installed, first experiment to
try out
-
Training: co-experts needed to run compton at 1 shift
per day
-
Alexandre Deur suggested moving the compton computer
and cameras to
the DAQ
room of the Counting House
Eugene Chudakov discussed the Moller
Polarimeter:
-
The detector will be replaced during the summer
-
Systematic error from the measurement is 3.4% (largest
from magnetization measurement)
-
Magnetization measurements at JLab and SLAC:
-
One 50 um foil measured with both methods at B > 70
Gauss
-
Results match within about 0.5% relative
Ole Hansen discussed analysis software:
-
For C++ analyzer status: prelim. tracking code
working, and has output trees
and basic
histograms (no cuts)
-
Things to do:
-
Bring tracking level to level of ESPACE (2 months)
-
Physics computations (1 month)
-
Flexible histogramming with cuts and expressions (2
months)
-
Missing items: FPP, systematic PID, and many
subtleties
-
New version of ESPACE: uses left/right naming
convention,
aerogel
and PR included, faster tracking code, and ready for use
Nilanga Liyanage discussed online
monitoring:
-
Ten days of commissioning to test
-
No major difference since last year. Same online
histograms
-
Use new version of ESPACE, which includes column-wise
ntuples
-
Need new database for optics
-
Alexandre Deur will setup online monitoring
Bob Michaels gave an update on the DAQ
and trigger systems:
-
New G0 helicity electronics not ready
-
Faster DAQ: 3 kHz per arm at 25% DT seems achievable
-
Need to check DAQ with beam
-
Scalers: have synchronous scaler events
-
Feedback: Joe Grames, Bob Michaels responsible, HAPPEX
quality,
and Feedback
on position