Minutes for Small Angle GDH Target
Meeting, click here.
Minutes for A1n Analysis Meeting,
click here.
Minutes for g2n Analysis Meeting,
click here.
Minutes for GDH Meeting, click here.
Tentative Date of next Collaboration
Meeting: December 6-7 2002
saGDH Septum and Commissioning Meeting
Kees
de Jager opened the meeting by discussing the schedule:
As long
as the first septum magnet arrives by November 11th, there is no change
in the short term schedule.
When the first septum arrives only basic inspections will
be made to insure that the magnet
was not damaged during delivery.
A contingency
plan has been developed for different possible scenarios in
case the septum isn't ready for the
December commissioning period.
Paul Brindza
discussed the status of the septum magnets:
If no major
problems develop, the first septum should be ready to ship by
October 29th and should be at Jlab
the first week of November. The voltage tap
resistors were moved out of the magnet
due to the unexplained failure of G0's
resistors. Also the relieve
values were checked due to the problem with G0's
burst disk.
The coil fitting
for the second magnet is well underway, but the magnet probably
will not be ready in under 4 months
and may take as long as 6 months.
Al Gavalya discussed
the design Status:
Design work
for saGDH is being finished. The design for the correction coil mounts
will be finished in the next week
by Joyce. Susan is finishing the collimator design,
and Al has been working on the coupling
extension tube for the downstream end.
Work to incorporate a new cell pull off design is also being discussed.
Steve Lassiter
discussed the field gradient due to the septum magnet:
Steve created
a better model to calculate the field gradient due to the presence of
the septum. From Steve's simulations,
field clamps will work. Most of the gradients
are below 30 mG/cm, expect for the
dBz/dy component, which is ~ 52 mG/cm using
+/- 10 cm above and below the beam
line in y.
Alexandre Deur
is working on correction coils to compensate for the remaining
gradients.
Scott
Higgins gave an update on the Septum controls:
Scott
has been working on getting things ready for when the PLC arrives.
The
field control software is ready for
the NMR probes. The interface software for the
PLC is finished and tested.
There will be supervisory controls to monitor the
magnets through EPICS and a few active
control points.
Controls for the gradient and correction coils will be available.
Alexandre
Deur discussed issues and preparation for the experiment:
Though the
experiment has been delayed, only one septum magnet will be ready
for the running period. Only
one good cell exists with the new Ice cone cell design.
The problem with production remains
unexplained.
Since the last
collaboration meeting, the field gradient problem has lessened
due to new calculations. Field
clamps will now be used with correction coils to
compensate for the gradients.
Designs for correction coils are being finished by
Al Gavalya. Once the design
and fabrication work is completed, the winding for
the coils will be done.
Due to the
rising tails seen during the original GDH experiment, saGDH requires
good beam quality and alignment.
After the commissioning period, Alexandre would
like to check the rising tails.
Doug Higinbotham
discussed the Septum Optics commissioning:
Doug will
be the run coordinator for the optics commissioning period, which is
scheduled for mid December.
One day is needed by John LeRose for the beam tune.
Carbon and elastic 3He
data will be taken at three beam energies.
Data was taken
with the spectrometers vacuum coupled to the scattering chamber.
There should be sufficient manpower
for the analysis.
Matt Poelker
discussed the Beam:
Able to achieve
~ 75% beam polarization and about 30 uA maximum current with
diode laser. Hall A will have
an independent current ramp to reduce affects to other
halls. Leakage from G0 beam
is very small
Xiaodong Jiang discussed helicity monitoring:
The
G0 helicity scheme will be used for saGDH. Helicity is predicted
and nobody
knows the helicity
in-time. It is important that scalers are recorded for each pulse.
Xiaodong had made the necessary changes in ESPACE to accommodate the helicity
scheme.
Source code was released October 17th. DAQ deadtime should be less
than
20 to 30%.
David Lhuillier
gave an update on the Compton polarimeter:
The main systematic
error is probably due to the calibration of the polarimeter.
New analysis code has been installed
on-line and is ready for use. Compton is very
sensitive to the beam quality, so
saGDH should try to get a good beam tune.
During the experiment a day will be
needed to check things out.
To get better
results at the lower energies, David will try to increase the gain and
do tests during the experiment.
Eugene Chudakov
discussed the Moller Polarimeter:
Moller
works fine with the new helicity scheme. Measurement error is dominated
by the polarization of the foil.
Systematic error for the measurement is 3.4%.
Bob Michaels
gave an update on the DAQ and Raster systems:
There
is a problem with the charge asymmetry. The charge asymmetry depends
on the helicity order RL vs LR.
A check will be made into the electronics and Parity
DAQ. It is hoped that installation
of a new high voltage switch will help fix the
problem.
An independent L-arm DAQ will be available.
Ron Gilman
discussed detectors:
The L-arm detectors
that will be used for saGDH are fine. The L-arm gas
Cherenkov has new PMTs. For
the R-arm Seonho Choi and Vince Sulkosky will
check the gas Cherenkov.
Nilanga Liyanage
discussed online monitoring:
For the optics
commissioning, the software is ready. Code to read scalers need
some work. Bob Michaels has
ROOT macros, if anyone wants to use them.
Seonho Choi will work on code for beam trips and beam ramping.