Laser System
- Assemble COMET Lasers (Chiranjib/Yi)
- Move in a Rack to new target lab for COMET Lasers
- Interlock connections to Lasers (Mark/Yi)
- Interlock connections in the Hall (Mark/Yi)
- RTDs for Laser enclosure (Done by Yi'/Yi)
- RTDs to readout chassis for interlock (Yi')
- Optics setup (Chiranjib/Jin)
- Optics alignment (Chiranjib/Jin/Yi'/Yi/Jian-ping)
- Camera (Jin)
- Spectrum analyzer (Yi)
- Q-wave plate stepping motor (Jin)
Oven and Heater
- Heater Installation (Joe)
- Heater Control Box and connection (Joe)
- Oven temperature control RTD (Yi')
- RTDs for He3 Cell and Reference Cell (Done by Yi'/Yi)
NMR System
- Longitudinal RF Coil Connection (Yi')
- Pickup Coil Cables (Chiranjib/Yi')
- VI update (Jin/Yi)
- NMR Lock-in repair (Yi)
EPR System
- EPR D2 assembly (Chiranjib/Yi)
- EPR RF Cable (Chiranjib/Yi')
Spin Flip
- Test plan (Yi/Jin)
- EPICS communication (Jin)
- VI update (Yi/Jin)
Holding Field
- Optimal Field determination (Yi')
- Correction Field Calculation (Yi')
- Correction Coil connection (Chiranjib/Yi')