Line 62: | Line 62: | ||
***Issue with CAEN HV for Hodoscope with EPICS | ***Issue with CAEN HV for Hodoscope with EPICS | ||
**Scalers | **Scalers | ||
+ | ***need cabling | ||
+ | ***need work on readout | ||
+ | ***need one SIS set to 3801 for helicity, rest 3800 | ||
+ | ***G0 scalers than can be used for detectors - need width at least 10 ns as input | ||
+ | ***FADC for BPM/raster + helicity signal | ||
+ | ***can add readout list | ||
+ | ***3820 cannot get it to work so far, will take it out - and work on it in TEDF | ||
**Recoil polarimeter | **Recoil polarimeter | ||
**EPICS | **EPICS | ||
+ | **BCM | ||
+ | ***plugged signal in analog receiver for upstream - 30 uA - will check signal in counting house | ||
+ | ***DAC input for VtoF | ||
+ | ***digital receiver - cable should still be connected as before | ||
+ | |||
**Helicity | **Helicity | ||
+ | ***erverything plugged in LHRS - still need L1A patch to scaler | ||
+ | *** code merged to readout list - can test it | ||
+ | *** last piece of helicity scaler from TEDF to be ported over to LHRS | ||
+ | *** finishing podd module for readout | ||
**start / stop / EPICS script | **start / stop / EPICS script | ||
+ | ***working on tedbbdaq for test setup | ||
+ | ***will update scripts on adaq | ||
*On-going tasks | *On-going tasks | ||
− | **Network setup ( done ) - SBS MPD side might need few cables - need pull network for SBS side (0%) | + | **Network setup ( done ) - SBS MPD side might need few cables - need pull network for SBS side (0%) - should check when bunker is setup |
− | **Scaler crate setup ( | + | **Scaler crate setup (90 % - Steve - need add readout) - Steve could not talk to CPU (done) - IP fixed with DHCP - need change fan tray - CAEN ( done ) |
**documentation of VME crate names to power cycle - need to make sure all VXS are in dhcp -Bryan ( done ) https://hallaweb.jlab.org/wiki/index.php/SBS_Network_Devices_in_Hall_A | **documentation of VME crate names to power cycle - need to make sure all VXS are in dhcp -Bryan ( done ) https://hallaweb.jlab.org/wiki/index.php/SBS_Network_Devices_in_Hall_A | ||
**3 rd GEM VXS crate install router moved up ( 100% ) | **3 rd GEM VXS crate install router moved up ( 100% ) | ||
Line 76: | Line 94: | ||
**boot VME controllers (100 % done - need ask hostname TS crate ) | **boot VME controllers (100 % done - need ask hostname TS crate ) | ||
**TS cables - all fibers plugged (done) - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS | **TS cables - all fibers plugged (done) - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS | ||
− | - new firmware for LHRS TI | + | - new firmware for LHRS TI - |
− | **detector cabling | + | **detector cabling ( 100 % - debugging ) |
− | **new MPD production - about to start - FPGA | + | **new MPD production - about to start - FPGA received by Paolo - need check when production starts |
**MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link | **MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link | ||
− | **MPD being setup in Hall A - need setup VTPs to boot (done ) - 10 gigE network plugged (done) - will be able to test in Hall A (done) - 5.2 KHz max trigger rate - 900 MB/s max per VTP - LV installed soon (done ) | + | **MPD being setup in Hall A - need setup VTPs to boot (done ) - 10 gigE network plugged (done) - will be able to test in Hall A (done) - 5.2 KHz max trigger rate - 900 MB/s max per VTP - LV installed soon (done ) |
− | **setup portservers : 1 4 port portserver for VTP (done), still need to set up a 8 port one and HCAL portserver | + | **setup portservers : 1 4 port portserver for VTP (done), still need to set up a 8 port one and HCAL portserver - need one more |
− | **need to install remote switch for crate in bunker (done hareboot32) - rest are VXS or VME64 - need put CAEN crate on network | + | **need to install remote switch for crate in bunker (done hareboot32) - rest are VXS or VME64 - need put CAEN crate on network |
− | **Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install | + | **Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install - might be ok with current NIM crate |
− | **TS setup - 90 % | + | **TS setup - 90 % - all cabled - still need to configs |
− | **Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup - need pull raster BPM BCM (0% will do it with David and Bob ) | + | **Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup - need pull raster BPM BCM (0% will do it with David and Bob, Jack Heidi helping ) |
**HCAL cabling ( done ) | **HCAL cabling ( done ) | ||
**HCAL need power ( done, Berta ) | **HCAL need power ( done, Berta ) | ||
Line 96: | Line 114: | ||
**Cosmics Hodoscope ( on-going ) | **Cosmics Hodoscope ( on-going ) | ||
**Cosmics Grinch | **Cosmics Grinch | ||
− | **Test 10 gig link to DAQ to adaq1 | + | **Test 10 gig link to DAQ to adaq1 - 900 MB/s - will try with two VTP |
+ | **New computers have been installed - Main DAQ computer still not received - | ||
**EPICS script - | **EPICS script - | ||
− | **alarm handler (David) | + | **alarm handler (David) - still need to set up on adaqsc - check with Ole to have hacweb7 online and copy - need to make sure audio avalable for alarm |
*Outstanding issues | *Outstanding issues | ||
**2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare ( done ) | **2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare ( done ) | ||
+ | 1 more bad FADC on shower ( 1 channel bad ) | ||
**SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) Hall B lending two - will get once checked | **SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) Hall B lending two - will get once checked | ||
− | **need to adjust for HCAL transit time with different PMTs | + | **need to adjust for HCAL transit time with different PMTs - looked at it already, about 12 ns - 20 cable after summing - still need to look with led |
− | **status of cosmics paddles ( installed by Bogdan ) | + | **status of cosmics paddles ( installed by Bogdan ) - HCAL paddles in test lab still need to be set up - Scott checked with techs - will push next week |
**GEM fibers too short : Mark will order parts - ( fiber ordered - + 2 extensions ordered ) | **GEM fibers too short : Mark will order parts - ( fiber ordered - + 2 extensions ordered ) | ||
− | **15 bad MPDs - need to look at fixing - Ben ? Dustin loaning us 6 MPDs - need 85 total - 67 in hand - 1 MPD (301) VME address issue in some slot - | + | **15 bad MPDs - need to look at fixing - Ben ? Dustin loaning us 6 MPDs - need 85 total - 67 in hand - 1 MPD (301) VME address issue in some slot - |
***APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir ) | ***APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir ) | ||
− | **GEM fiber possibly bad - 2 broken - if long sleeve want to pull spare in separate conduit ( | + | **GEM fiber possibly bad - 2 broken - if long sleeve want to pull spare in separate conduit ( extension setup - 50 % ) |
**GEM HV IP need setup ( Alex ) Done | **GEM HV IP need setup ( Alex ) Done | ||
**GEM clock/trigger box for BB side ( got one from UVA ) | **GEM clock/trigger box for BB side ( got one from UVA ) | ||
**GEM LV remote control ( done ) | **GEM LV remote control ( done ) | ||
**GEM VTP transceivers hanging - ( swapped with SSP - firmware fix will be implemented ) | **GEM VTP transceivers hanging - ( swapped with SSP - firmware fix will be implemented ) | ||
+ | **SBS bunker cables | ||
+ | ***fiber order | ||
+ | ***test multiple event builder soon | ||
*Status software in a-onl@aonl1 | *Status software in a-onl@aonl1 | ||
*GRINCH | *GRINCH | ||
+ | **still need to install - need to check if commits were merged | ||
*Shower | *Shower | ||
+ | **installed | ||
*GEM | *GEM | ||
+ | **Andrew still need to set it up there | ||
*Hodoscope | *Hodoscope | ||
+ | **installed | ||
*HCAL | *HCAL | ||
+ | **setup and can look at data | ||
+ | |||
+ | |||
+ | *All crates | ||
+ | **want run GEM and shower | ||
+ | **readout list ready - just need CODA configs | ||
+ | **TS for V792 gate | ||
+ | |||
+ | *coincidence Shower and hodoscope in TS2 of GEM |
Latest revision as of 11:45, 27 August 2021
- Updates
- HCal
- All ADC and TDC working, all signals seems ok
- adding new FADC for reference channel and supercluster
- F1 TDC with reference time, still need to check to get it to work - hope to finish today
- will take cosmics
- pulser setup for coincidence trigger check next
- Bigbite Shower
- finished mapping checks : turning one column at a time, found a couple cables swapped, fixed, done
- pulser test : pulser at detector end and look in FADC, compared amplitude of FADC with scope to evaluate attenuation
- issue with summing module
- one FADC not working
- one fan in /out module not working
- debugging
- estimate few days to finish debugging
- after look at calibration code
- fan/in out module : F428 - two main locations : cabinet outside SBS bunker detector 1 or 2 and 1 cabinet in LHRS - might need
- starting discussion of coincidence trigger with Bob and Scott
- cosmics run take - but still need to check plots
- Bigbite Hodoscope
- TDC extension installed, TDC look good for every channel
- ADC cables look goof
- new LV for NINO received ( goes up to 20 V ) NINO working
- HV working with telnet, Steve fixed EPICS issue
- will set HV as before
- Mark setup trigger for cosmics
- can take data
- SBS offline updated software will be installed
- working on How-to for shift takers
- still hoping to get compress air for housing of PMT to avoid He poisoning
- Mark setup hodoscope trigger
- GRINCH
- all channels connected and look ok with HV
- debugging a few empty TDC channels
- ADC repaired one ADC cable : all ADC cable should work
- run CODA
- just need to set trigger and gate for cosmics
- two NINO cards need to be replaced ( at top of GRINCH ) need fall protection set up, might need to use lift
- found connection for LED and pulser working
- CODA working
- old gate should still be set up
- LHRS
- Fiber to TI connected, need to get new firmware for the TI received this morning.
- will need updated TI library and can give it a try
- running cables from LHRS, BCM to SBS bunker, will add a new cable tray, see HALOG
- new router installed, HRS DAQ working fine after
- can use with one VXS crate with current firmware / library
- CDet
- reviewed all pixels on half module, will revised resistors of some of them
- new data with new resistors take and will be analyzed
- GEM BigBite
- all electronics connected working
- INFN has noise issue being investigated
- HV on one module
- UVA side everything connected and looks file : took data for 2 days, can see signals but full analysis still on-going
- all cosmics data taken with VTP : 20 M events
- took overnight data without zero supress, last night was taken zero supression
- could 5.2 KHz with zero supression as long as we don't reach 900 MB/s
- RF time
- need add TDC
- HV
- Issue with CAEN HV for Hodoscope with EPICS
- Scalers
- need cabling
- need work on readout
- need one SIS set to 3801 for helicity, rest 3800
- G0 scalers than can be used for detectors - need width at least 10 ns as input
- FADC for BPM/raster + helicity signal
- can add readout list
- 3820 cannot get it to work so far, will take it out - and work on it in TEDF
- Recoil polarimeter
- EPICS
- BCM
- plugged signal in analog receiver for upstream - 30 uA - will check signal in counting house
- DAC input for VtoF
- digital receiver - cable should still be connected as before
- HCal
- Helicity
- erverything plugged in LHRS - still need L1A patch to scaler
- code merged to readout list - can test it
- last piece of helicity scaler from TEDF to be ported over to LHRS
- finishing podd module for readout
- start / stop / EPICS script
- working on tedbbdaq for test setup
- will update scripts on adaq
- Helicity
- On-going tasks
- Network setup ( done ) - SBS MPD side might need few cables - need pull network for SBS side (0%) - should check when bunker is setup
- Scaler crate setup (90 % - Steve - need add readout) - Steve could not talk to CPU (done) - IP fixed with DHCP - need change fan tray - CAEN ( done )
- documentation of VME crate names to power cycle - need to make sure all VXS are in dhcp -Bryan ( done ) https://hallaweb.jlab.org/wiki/index.php/SBS_Network_Devices_in_Hall_A
- 3 rd GEM VXS crate install router moved up ( 100% )
- need power and network in GEM bunker ( done )
- boot VME controllers (100 % done - need ask hostname TS crate )
- TS cables - all fibers plugged (done) - will post informations -hodoscope / grinch/ shower separate - can be combined at any time now everything plugged to TS
- new firmware for LHRS TI -
- detector cabling ( 100 % - debugging )
- new MPD production - about to start - FPGA received by Paolo - need check when production starts
- MPD VTP readout - on-going in daq lab - still having issue getting APV sending data to MPD - events going through high speed link
- MPD being setup in Hall A - need setup VTPs to boot (done ) - 10 gigE network plugged (done) - will be able to test in Hall A (done) - 5.2 KHz max trigger rate - 900 MB/s max per VTP - LV installed soon (done )
- setup portservers : 1 4 port portserver for VTP (done), still need to set up a 8 port one and HCAL portserver - need one more
- need to install remote switch for crate in bunker (done hareboot32) - rest are VXS or VME64 - need put CAEN crate on network
- Bigbite - HCal trigger setup - need check with Bob if additionnal NIM crate need to be install - might be ok with current NIM crate
- TS setup - 90 % - all cabled - still need to configs
- Beamline crate setup ( in scaler crate ) - FADC is in scaler need to be setup - need pull raster BPM BCM (0% will do it with David and Bob, Jack Heidi helping )
- HCAL cabling ( done )
- HCAL need power ( done, Berta )
- Mark hodoscope trigger ( done )
- Computer move to Hall A : sbsdaq1/2/3 tedbbdaq (done ) enpcamsonne ( done ) - need to install X server - Need ask Ole -
- LHRS fiber pull ( waiting fiber August 13th ) - most likely LHRS at end of SBS run (done )
- Cosmics trigger ( done ) -
- Cosmics HCAL ( ongoing )
- Cosmics Shower ( on going )
- Cosmics Hodoscope ( on-going )
- Cosmics Grinch
- Test 10 gig link to DAQ to adaq1 - 900 MB/s - will try with two VTP
- New computers have been installed - Main DAQ computer still not received -
- EPICS script -
- alarm handler (David) - still need to set up on adaqsc - check with Ole to have hacweb7 online and copy - need to make sure audio avalable for alarm
- Outstanding issues
- 2 bad FADCs Bigbite - 1 FADC was repaired - one being repaired - 1 Compton FADC - repaired can use as spare ( done )
1 more bad FADC on shower ( 1 channel bad )
- SD delay : still need 2 SDs ( Glasgow and INFN just requested quote ) Hall B lending two - will get once checked
- need to adjust for HCAL transit time with different PMTs - looked at it already, about 12 ns - 20 cable after summing - still need to look with led
- status of cosmics paddles ( installed by Bogdan ) - HCAL paddles in test lab still need to be set up - Scott checked with techs - will push next week
- GEM fibers too short : Mark will order parts - ( fiber ordered - + 2 extensions ordered )
- 15 bad MPDs - need to look at fixing - Ben ? Dustin loaning us 6 MPDs - need 85 total - 67 in hand - 1 MPD (301) VME address issue in some slot -
- APV needed 1208 - 966 in hand working - Michael might lend 40 - ( check with Thir )
- GEM fiber possibly bad - 2 broken - if long sleeve want to pull spare in separate conduit ( extension setup - 50 % )
- GEM HV IP need setup ( Alex ) Done
- GEM clock/trigger box for BB side ( got one from UVA )
- GEM LV remote control ( done )
- GEM VTP transceivers hanging - ( swapped with SSP - firmware fix will be implemented )
- SBS bunker cables
- fiber order
- test multiple event builder soon
- Status software in a-onl@aonl1
- GRINCH
- still need to install - need to check if commits were merged
- Shower
- installed
- GEM
- Andrew still need to set it up there
- Hodoscope
- installed
- HCAL
- setup and can look at data
- All crates
- want run GEM and shower
- readout list ready - just need CODA configs
- TS for V792 gate
- coincidence Shower and hodoscope in TS2 of GEM