Monday, October 7, 2013 2:00pm EST
From Hall A Wiki
Last meeting: Tuesday, September 17, 2013 2:00pm EST
Agenda
- Update from KK/Tyler
- Update from Juliette
- Update from Jason .pptx .pdf
- Update from Jim .pptx .pdf
- Update from Ernie
Minutes
Attending: Juliette, Tyler, KK, Jim, Jason, Ernie, Cathy
- Tyler/KK - had iteration with Jason
- Tyler will make new pictures for Wednesday as backup
- Juliette
- get somewhat similar optics back with iron, but with only 20% decrease in current density
- Jason - Carrier
- went through iteration with Tyler
- will probably need to trim acceptance to support coils
- Jim - Vacuum vessel
- 9 tons
- better with real vacuum attachments upstream and downstream
- plan to cost the materials
- plate is very large - mill run
- petal pipe - having trouble getting supports in - will affect acceptance
- if (iron free) SS - easier to weld, but not as strong, more weight
- will investigate iron if we have to as a backup
- need service ports and pumping ports
- Ernie
- needs to know where the services go (talk to Juliette)
For Wednesday (update - extensive though it is!):
- Juliette - no negative bend, iron in coils
- Jason - coil carrier FEA
- Jim - vacuum vessel FEA
For Monday (more comprehensive):
- Times are internal and suggested only - looking at a 2.5 hour meeting...
- KK - experiment overview (10 minutes + 10 minutes?)
- Juliette - magnet overview (somewhat historical) (30 minutes + 15 minutes?)
- Ernie - water-cooling and infrastructure (15 minutes + 15 minutes?)
- Jason - Coil carrier and supports FEA (30 minutes + 15 minutes?)
- Jim - Vacuum vessel FEA (15 minutes + 15 minutes?)