Difference between revisions of "Docs"
From Hall A Wiki
(→Schematics) |
(→Mapping Documents) |
||
Line 10: | Line 10: | ||
===Mapping Documents=== | ===Mapping Documents=== | ||
*Updated complete mapping for cosmics running 2021 '''currently in preparation''' | *Updated complete mapping for cosmics running 2021 '''currently in preparation''' | ||
− | *Cosmics Channel Mapping (February | + | *Cosmics Channel Mapping (R. Montgomery, February 2020) [[https://hallaweb.jlab.org/wiki/images/0/0c/BB_HODO_Channel_Map.pdf]] |
− | *High voltage and low voltage mapping Feb 2020 overview [[https://hallaweb.jlab.org/wiki/images/8/8f/HodoMapping_Feb2020_lowres.pdf]] | + | *High voltage and low voltage mapping Feb 2020 overview (R. Montgomery, February 2020) [[https://hallaweb.jlab.org/wiki/images/8/8f/HodoMapping_Feb2020_lowres.pdf]] |
− | *Mapping document Feb 2020, take note there are 3 tabs in the spreadsheet. This mapping misses signal cables from frame to weldment [[https://hallaweb.jlab.org/wiki/images/a/ad/HodoMapping_Feb2020.xlsx]] | + | *Mapping document (R. Montgomery, Feb 2020), take note there are 3 tabs in the spreadsheet. This mapping misses only signal cables from frame to weldment [[https://hallaweb.jlab.org/wiki/images/a/ad/HodoMapping_Feb2020.xlsx]] |
===Schematics=== | ===Schematics=== |
Revision as of 12:07, 26 March 2021
Contents
General Documents
- BigBite Timing hodoscope Technical Specifications (design and performance requirements), J. Annand et al. [[1]]
- Software requirements, R. Montgomery et al. [[2]]
- Original electronics plan, J. Annand et al. (describes chain from PMT to final VME readout, including high voltage and low voltage)[[3]]
- Scintillator bar and light guide surface roughening tests in Glasgow 2020, R. Montgomery et al. [[4]]
How to Documents
- High voltage and low voltage set up and operation for hodoscope in TEDf with cosmics, J. Annand et al. [[5]]
Mapping Documents
- Updated complete mapping for cosmics running 2021 currently in preparation
- Cosmics Channel Mapping (R. Montgomery, February 2020) [[6]]
- High voltage and low voltage mapping Feb 2020 overview (R. Montgomery, February 2020) [[7]]
- Mapping document (R. Montgomery, Feb 2020), take note there are 3 tabs in the spreadsheet. This mapping misses only signal cables from frame to weldment [[8]]
Schematics
- HV patch panels, J. Annand, A. Clarkson [[9]]
- Schematic for LV distributor panel is found in figure 5 of "Original electronics plan" document [[10]]
- Schematic for PMT bases is found in figure 3 of "Original electronics plan" document [[11]]
- Schematic of NINO front end cards is found in figure 4 of "Original electronics plan" document [[12]]
Manuals/Spec sheets for components of hodoscope
- Electron Tubes ET9124 SB type PMTs [[13]]
- Eljen Technology EJ200 scintillator bars [[14]]
- Eljen technology UVT acrylic light guides [[15]]
- DYMAX optical cure epoxy - check which specific model number was used in Jlab repairs
- Cage HV connectors at HV patch panel connections [[16]]
- CAEN V792 [[17]]
- CAEN V1190 [[18]]
- CAEN SY1527LC HV mainframe, 19" wide, 8U [[19]]
- Accessory CAEN A1932AN 48 channel HV distributer modules for mainframe [[20]]
- Accessory CAEN A1531 primary PSU for HV mainframe - no specific manual online, contacted CAEN and they refer to this document [[21]]
- AGILENT N5761A DC power supply unit for NINO front end cards, 19" wide, 1U, rack-mountable [[22]]
- Wiener 6U VME64x 6023 crate [[23]]