Line 8: | Line 8: | ||
== Detectors == | == Detectors == | ||
− | + | * [[BigBite HV GUI]] (updated 23 April 2009) | |
* [[High Voltage GUI for BigBite (Wire Chamber, Scintillator and Shower)]] | * [[High Voltage GUI for BigBite (Wire Chamber, Scintillator and Shower)]] | ||
* [[Change Wire Chamber Threshold]] | * [[Change Wire Chamber Threshold]] | ||
+ | * [[Recover after BigBite CAMAC reset]] | ||
* [[How to set BigBite Total Shower thresholds]] | * [[How to set BigBite Total Shower thresholds]] | ||
* [[BigBite Wire Chamber Trip Recover Procedure]] | * [[BigBite Wire Chamber Trip Recover Procedure]] | ||
Line 16: | Line 17: | ||
* [[RICH pedestal run]] | * [[RICH pedestal run]] | ||
* [[Scaler problem]] ''or'' "Scaler problem: Please check the web page" | * [[Scaler problem]] ''or'' "Scaler problem: Please check the web page" | ||
+ | * [[How to calibrate shower and preshower with cosmics]] | ||
+ | * [[Neutron Detector]] | ||
== Polarized He3 Target == | == Polarized He3 Target == | ||
Line 26: | Line 29: | ||
* [[Oven Control]] | * [[Oven Control]] | ||
* [[Special Procedure For Moving Target]] | * [[Special Procedure For Moving Target]] | ||
+ | * [[Beam Recovery Procedure]] | ||
== Run sheets and shift checklist == | == Run sheets and shift checklist == |
Latest revision as of 15:08, 6 May 2009
Here is shift index page of worker HowTo for experiment transversity.
General
- Data Replay
- Experts On-Call
- Database: http://hallaweb.jlab.org/experiment/transversity/rundb/db_halla_wei/
Detectors
- BigBite HV GUI (updated 23 April 2009)
- High Voltage GUI for BigBite (Wire Chamber, Scintillator and Shower)
- Change Wire Chamber Threshold
- Recover after BigBite CAMAC reset
- How to set BigBite Total Shower thresholds
- BigBite Wire Chamber Trip Recover Procedure
- How to reboot TS12 ROC5-10
- RICH pedestal run
- Scaler problem or "Scaler problem: Please check the web page"
- How to calibrate shower and preshower with cosmics
- Neutron Detector
Polarized He3 Target
- Target Operator Check List
- Spin Flip System
- Holding Field Control
- Target Slow Control
- NMR Measurement
- Oven Control
- Special Procedure For Moving Target
- Beam Recovery Procedure
Run sheets and shift checklist
Commissioning run sheet ps file and tex file
Production run sheet ps file and tex file
Production beam charge accumulation sheet ps file